10/11/19: Driveway Replacement Project

 

New Canaan Field Club
   Driveway Replacement Project

10/11/19

Dear Members,

Here is a quick update on the driveway. The project is progressing well and quickly. Here are some updated guidelines and schedules. Please note that everything is weather dependent.

  • At all times, daytime parking or access to the club’s driveway remains restricted and not possible. Evenings are fine. Please be aware of rough and uneven areas. Please stay clear of all equipment and machinery, consider car pooling, parking carefully on grass area by pro house, or Glen Drive.

  • Today/tomorrow/Monday: catch basins to be installed, grading continues, and dig out gravel parking areas

  • Monday & Tuesday: binder and paving processes begin
    We expect the project complete towards the end of next week. Additional information will be made available next week and as the work progresses. I thank you in advance for your understanding.

Please reach out with any questions or concerns.

Thanks,

Oli

Oli Olafsson
Vice-president/Operations