10/4/19: Driveway Project Update

 

New Canaan Field Club
   

Driveway Replacement Project

10/4/19

Dear Members,

Driveway Makeover starts on Monday! As previously announced, we are proceeding to replace our driveway between Tennis and Route 123, including the driveway at the Pro House. This is funded from our existing reserve budget. 

Below are some important guidelines to follow while we have heavy equipment and trucks coming and going during the day.

  • At all times, parking or access to the club’s driveway during the day is restricted and generally not possible – evening access by car is fine. Please be aware of rough and uneven areas. Please stay clear of all equipment and machinery and consider car pooling and parking on Glen Drive or in other safe out-of-the-way areas. Paddle and tennis courts remain open.
     
  • Monday and Tuesday, October 7th & 8th: removal of asphalt. Evening access is fine.
     
  • Wednesday and Thursday, October 9th and 10th: Grading begins and catch basins will be installed near Rte 123 to improve water drainage and to prevent ice buildup during winter months. Evening access is fine.


Additional information will be made available next week and as the work progresses. I thank you in advance for your understanding.

Please reach out with any questions or concerns.

Thanks,
Oli 

Oli Olafsson
Vice-president/Operations