10/15/19: Driveway Update

 

New Canaan Field Club   

Driveway Replacement Project

10/15/19

Dear Members,

Here is a quick update on the driveway. Paving has begun. Please note that the schedule remains weather dependent.

  • At all times, daytime parking or access to the club’s driveway remains restricted and not possible. Please stay clear of all equipment and machinery, consider car pooling, parking carefully on grass area by pro house, or Glen Drive.

  • Binding & Paving has begun and is scheduled to complete by Thursday. Please do not drive or park on new asphalt at this time.

  • Curbing and speed bumps are scheduled to be completed on Friday and we expect everything to be finished up by end of day.

  • Additional information will be made available, as needed. I thank you in advance for your understanding.
    Please reach out with any questions or concerns.

Thanks,

Please reach out with any questions or concerns.

Thanks,
Oli 


Oli Olafsson